[1]刘兴邦,汪宏辉,王 淦,等.水网地区大直径长输管道自动焊施工适应性研究[J].焊管,2022,45(7):52-56.[doi:10.19291/j.cnki.1001-3938.2022.07.010]
 LIU Xingbang,WANG Honghui,WANG Gan,et al.Research on the Adaptability of Automatic Welding Construction of Large-diameter Long-distance Pipeline in Water Areas[J].,2022,45(7):52-56.[doi:10.19291/j.cnki.1001-3938.2022.07.010]
点击复制

水网地区大直径长输管道自动焊施工适应性研究()
分享到:

《焊管》[ISSN:1001-3938/CN:61-1160/TE]

卷:
45
期数:
2022年第7期
页码:
52-56
栏目:
经验交流
出版日期:
2022-07-28

文章信息/Info

Title:
Research on the Adaptability of Automatic Welding Construction of Large-diameter Long-distance Pipeline in Water Areas
文章编号:
10.19291/j.cnki.1001-3938.2022.07.010
作者:
刘兴邦汪宏辉王 淦高 鹏周洪云贾继聪
1.中石化江苏油建工程有限公司,江苏 扬州 225126;2.国家管网集团江苏天然气管道有限责任公司,南京 210000
Author(s):
LIU XingbangWANG HonghuiWANG GanGAO PengZHOU HongyunJIA Jicong
1.Sinopec Petroleum Engineering & Construction Jiangsu Corporation,Yangzhou 225126,Jiangsu,China;2.Pipechina Group Jiangsu Natural Gas Pipeline Co.,Ltd.,Nanjing 210000,China
关键词:
水网地区大直径长输管道全自动焊接焊接质量控制
Keywords:
water arealarge-diameter long-distance pipelinefully automatic weldingwelding quality control
分类号:
TG444.2
DOI:
10.19291/j.cnki.1001-3938.2022.07.010
文献标志码:
B
摘要:
针对水网地区大直径长输管道施工过程中存在的设备行走困难、施工带承载力差、焊接质量不稳定等问题,从线路优化、设备改造、施工带改造、机组配置优化等方面进行了管道自动焊施工的适应性研究,并从施工方案和工艺规程制定、焊接前准备以及焊接过程控制等方面提出了针对性的焊接质量控制措施。优化后的管道自动焊施工技术经过项目施工验证,不仅降低了水网地区管道施工难度,提升了施工效率,而且充分发挥了全自动焊接技术高效、高质量和高稳定性的特点,证明了全自动焊在水网地区大直径长输管道施工中的可行性,为自动焊技术在水网地区管道施工中的推广提供了依据。
Abstract:
In view of the problems in the construction of large-diameter long-distance transmission pipelines in water network area,such as difficulties in equipment travel,poor bearing capacity of construction zone and unstable welding quality,the adaptability of pipeline automatic welding construction is studied from the aspects of line optimization,equipment transformation,construction zone transformation and unit configuration optimization.Targeted welding quality control measures are put forward from the aspects of pre-welding preparation and welding process control.The optimized pipeline automatic welding construction technology has been verified by the project construction,which not only reduces the difficulty of pipeline construction in water network areas and improves the construction efficiency,but also gives full play to the characteristics of high efficiency,high quality and high stability of automatic welding technology,and proves the feasibility of fully automatic welding in the construction of large-diameter long-distance pipeline in water network areas.It also provides a basis for the popularization of automatic welding technology in the construction of water network lots.

参考文献/References:

[1]胡建春,陈龙,廖井洲.大直径X80油气输送管道焊接技术[J].焊管,2012,35(8):19-22.[2]薛振奎,隋永莉.焊接新技术在我国管道建设中的应用[J].焊管,2010,33(4):58-61.[3]樊学华,庄贵涛,李向阳,等.长输油气管道焊接方法选用原则[J].油气储运,2014,33(8):885-890.[4]高云青,王纪,李颂宏.X80级管线钢全自动焊焊接工艺[J].焊接技术,2010,39(1):69-70.[5]伍奕,荣军,万代强,等.Φ1 422 mm大口径X80钢管道全自动焊接技术应用[J].石油化工设备,2016,45(6):57-61.[6]于英姿,郑照东,张占辉.自动焊技术在长输管道焊接中的应用[J].焊管,2001(2):47-49,55.[7]吴宏,周剑琴.国内大口径、高钢级管道焊接及焊缝检测技术现状[J].油气储运,2017,36(1):21-27.[8]高云强.X80钢管道全位置机动焊工艺可行性研究[J].石油化工设备技术,2021,42(4):56-61[9]熊林玉,杜则裕,陶勇寅,等.X80钢管的焊接[J].油气储运,2003(10):53-56,60.[10]张小强,蒋庆梅,李朝.自动焊在中俄东线天然气管道工程试验段的应用[J].焊接技术,2017,46(9):92-94.[11]隋永莉.长输油气管道高强度管线钢管现场焊接技术[J].电焊机,2014,44(5):27-32.[12]隋永莉.我国长输管道建设对焊接技术发展的需求[J].金属加工(热加工),2015(6):43-44.[13]汪宏辉,李熙岩,张波,等.长输管道全自动焊接边缘未熔合产生原因与抑制技术[J].电焊机,2019,49(3):57-61.[14]颜爱政,刘华,刘雷,等.长输油气管道焊接技术的应用[J].油气储运,2008(8):40-43,61.[15]张志强,王海民,张建军,等.潮湿水网地区管道焊接技术[J].焊接技术,2013,42(2):72-74.[16]张晨,柳志伟,王喜卓,等.青宁天然气管道水网地带焊接缺陷及质量控制[J].石化技术,2019,26(11):6-8.[17]李艳华.西气东输管道江南水网地区的施工方法[J].油气储运,2003(5):27-29,61.[18]高永,张世彬,涂立成,等.浅谈江南水网地段大口径管道水田施工方法[J].油气田地面工程,2002(2):29.[19]王岩.水网地段大口径油气管道的沉管下沟施工[J].石油工程建设,2003(3):59-60.[20]许怀丽.水网地段大口径输水管网施工方法的研究[J].工程建设与设计,2013(11):120-122.[21]李广远,丁信东.西气东输水网地段管道施工系列方法和技术[J].石油工程建设,2004(4):6-10.

备注/Memo

备注/Memo:
收稿日期: 2021-11-27译者简介:刘兴邦(1986—),男,2010年本科毕业于哈尔滨工业大学焊接技术与工程专业,现主要从事长输管道焊接技术、施工管理方向的研究工作。
更新日期/Last Update: 2022-07-29